ONE STOP CENTRE (OSC) UNIT
OSC Customer Charter
-
To simultaneously process applications for Build Then Sell Concept, High Impact Projects and Foreign Investments as well as government projects within the period of 4 to 6 months from the date complete application is received.
-
To process applications simultaneously for Sell Then Build within 6 months from the date complete application is received.
- To ensure applications for planning proposal received at One Stop Centre are processed in no more than the period stated by the Ministry of Housing and Local Authority according to the following types of applications:-
Types of Application
No of Processing Days
a
4 simultaneous applications *
111 Days
b
3 simultaneous applications (involving land matters)
111 Days
c
3 simultaneous applications (do not involve land matters)
80 Days
d
2 simultaneous applications (involving land matters)
108 Days
e
2 simultaneous applications (do not involve land matters)
80 Days
f
Planning Approval
57 Days
g
Application for Engineering Plans
57 Days
h
Application for Building Plans
69 Days
* Involving applications for land matters, Planning Approval, Engineering Approval and Building Plans.
-
To prepare and distribute meeting decisions to applicants latest by 7 days after meeting is held.